HMA PAVEMENT OVERLAY WORK – SCHEDULE UPDATE
Due to recent rains, the schedule for upcoming HMA pavement overlay work in Norton Shores has been adjusted.
Please see the updated schedule below:
TUESDAY, SEPTEMBER 15
Overlays: Hughes Ave, Norman St, Bellevue Rd, Liberty Rd & Bundt Dr
Patching: Dorset Ln
WEDNESDAY, SEPTEMBER 16
Raising structures: Dorset Ln & Edenbrook Ct
Lowering structures: Mt. Garfield Rd
THURSDAY, SEPTEMBER 17
Overlays: Columbus Ave, Bloomfield Ct, Lake Point Dr, North Ln, Harbor Point Dr & Harbor Point Ct
FRIDAY, SEPTEMBER 18
Overlays: McDowell St, Shady Creek Dr, Dorset Ln & Edenbrook Ct
LOOKING AHEAD: SEPTEMBER 21–25
Monday, September 21 at the earliest:
• Martin Rd – Overlay
Tuesday, September 22 at the earliest:
• Canterbury Ave – Overlay
• Norwich Ave – Overlay
• McDermott St – Overlay
TRAFFIC INFORMATION:
Traffic will be controlled by signs and flaggers, and motorists should expect delays while work is underway. Please slow down and use caution when traveling through active work areas.
MOUNT GARFIELD ROAD:
The schedule for work on Mount Garfield Road east of Grand Haven Road is still being finalized and will be shared once it is established.
Please keep in mind that the schedule may change due to weather conditions.